As part of the 2023 Road Plan and in preparation for paving that is tentatively scheduled for September, the Highway Department will begin prepping the following roadways:
Week of 6/26/23
Old Mill Lane (from the bridge to dead end) – hot top removal and regrading
Week of 7/10/23
Willey Street Extension and Stevens Court – hot top removal
Week of 7/24/23
Locust Street (from Main Street to Pine Street) – sidewalk and curb removal.
*Road reclaim and regrade will occur later in the summer.
Week of 8/7/23
Partridge Lane – hot top removal, sewer line repair and culvert replacement
Week of 8/14/23
Watson Lane – roadway rebuild
The above dates are tentative and subject to change.
Thank you in advance for your cooperation and patience.
George Guilmette
Road Agent