Paving Updates

Week of November 20th
Paving on Locust Street, Stevens Court and Willey Street Extension is scheduled for Wednesday, November 22nd. Grading work is scheduled for Monday, November 20th and Tuesday, November 21st.
Week of November 27th
Paving on Watson Lane is scheduled for Monday, November 27th. Paving on Old Mill Lane and Partridge Lane will follow later in the week.
We do not anticipate further delays, however if there are any changes to the schedule, an update will be provided.
If you have any questions, please email [email protected] or [email protected].
Thank you for your continued patience.

Locust Street Roadwork and Paving Update

Additional work is required on Locust Street before the sidewalks and the road itself can be paved. In the meantime, the unpaved sidewalks are accessible and usable. 
 
The Highway Department is currently looking at the end of September/early October for paving to occur. An update will be provided when the schedule is confirmed.
If you have any questions, please email the Road Agent or the Town Administrator.
Thank you for your patience and understanding.

Message from the Rollinsford Highway Department: Road Prep Schedule

As part of the 2023 Road Plan and in preparation for paving that is tentatively scheduled for September, the Highway Department will begin prepping the following roadways:
Week of 6/26/23
Old Mill Lane (from the bridge to dead end) – hot top removal and regrading
Week of 7/10/23
Willey Street Extension and Stevens Court – hot top removal
Week of 7/24/23
Locust Street (from Main Street to Pine Street) – sidewalk and curb removal.
*Road reclaim and regrade will occur later in the summer.
Week of 8/7/23
Partridge Lane – hot top removal, sewer line repair and culvert replacement
Week of 8/14/23
Watson Lane – roadway rebuild
The above dates are tentative and subject to change.
Thank you in advance for your cooperation and patience.
George Guilmette
Road Agent

Upcoming Road Construction Beginning 10.4.22

Beginning October 4th, Brox Industries will begin reclaiming and regrading Jesse Doe Rd. Traffic in this area will be slow but passable and the transfer station will be open regular hours during construction.

After completing the work on Jessie Doe Road, crews will be moving to Beccaris Dr. to do the same. The road will be open to local traffic and emergency vehicles.

Please be extra cautious and attentive in these areas while work is underway.

Parking Ban 2.25.22-2.26.22

Due to the anticipated storm, a parking ban will be in effect from 12:01am Friday, February 25th through noon on Saturday, February 26th.

There will be NO ON STREET PARKING allowed during this time. Vehicles found parked on the street that are hindering snow removal are subject to being ticketed and towed.

Plow Truck Drivers Wanted

The Town of Rollinsford is looking for a part-time plow truck driver. Applicants must:
1. Be available for most storms within the winter season.
2. Be able to sit for long periods of time.
3. Have a safe driving history.

A CDL-B with air brake endorsement is preferred, but not required.

Job Type: Part-time

Salary: $20.00 /hour

Applications or resumes can be dropped off at the Highway Department garage (35 Jessie Doe Road) or sent via email.

Clement Road Paving Update

The contractor is preparing for paving Tuesday, September 14th, and paving is currently scheduled for Friday, September 17th. Clement Road will be closed part of day tomorrow with resident access only and closed all day Friday we will try to keep open to residents and emergency vehicles as much as possible. This is challenging with the road being so narrow and paving equipment being wide. PLEASE PLAN AN ALTERNATE ROUTE.