Message from the Rollinsford Highway Department: Road Prep Schedule

As part of the 2023 Road Plan and in preparation for paving that is tentatively scheduled for September, the Highway Department will begin prepping the following roadways:
Week of 6/26/23
Old Mill Lane (from the bridge to dead end) – hot top removal and regrading
Week of 7/10/23
Willey Street Extension and Stevens Court – hot top removal
Week of 7/24/23
Locust Street (from Main Street to Pine Street) – sidewalk and curb removal.
*Road reclaim and regrade will occur later in the summer.
Week of 8/7/23
Partridge Lane – hot top removal, sewer line repair and culvert replacement
Week of 8/14/23
Watson Lane – roadway rebuild
The above dates are tentative and subject to change.
Thank you in advance for your cooperation and patience.
George Guilmette
Road Agent

Upcoming Road Construction Beginning 10.4.22

Beginning October 4th, Brox Industries will begin reclaiming and regrading Jesse Doe Rd. Traffic in this area will be slow but passable and the transfer station will be open regular hours during construction.

After completing the work on Jessie Doe Road, crews will be moving to Beccaris Dr. to do the same. The road will be open to local traffic and emergency vehicles.

Please be extra cautious and attentive in these areas while work is underway.

Parking Ban 2.25.22-2.26.22

Due to the anticipated storm, a parking ban will be in effect from 12:01am Friday, February 25th through noon on Saturday, February 26th.

There will be NO ON STREET PARKING allowed during this time. Vehicles found parked on the street that are hindering snow removal are subject to being ticketed and towed.

Plow Truck Drivers Wanted

The Town of Rollinsford is looking for a part-time plow truck driver. Applicants must:
1. Be available for most storms within the winter season.
2. Be able to sit for long periods of time.
3. Have a safe driving history.

A CDL-B with air brake endorsement is preferred, but not required.

Job Type: Part-time

Salary: $20.00 /hour

Applications or resumes can be dropped off at the Highway Department garage (35 Jessie Doe Road) or sent via email.

Clement Road Paving Update

The contractor is preparing for paving Tuesday, September 14th, and paving is currently scheduled for Friday, September 17th. Clement Road will be closed part of day tomorrow with resident access only and closed all day Friday we will try to keep open to residents and emergency vehicles as much as possible. This is challenging with the road being so narrow and paving equipment being wide. PLEASE PLAN AN ALTERNATE ROUTE.

Sligo Road Closure

Road work including paving will be taking place on Sligo Road throughout the month of May. The road will be closed during the day from Pinch Hill Road to Portland Avenue. Please seek an alternate route. The farm will remain open and accessible.